Engineering Projects
Copper String 2032 Transmission Power Line Construction
CPB Contractors
-
The project Copper String 2032 involves the construction of a power
line from Townsville to Mount Isa, spanning about 1000km. The scope of
works include the construction of multiple powerline towers of variable
sizes, as well as multiple sub-stations in all the major towns in between
the two end points.
-
I have experience working in assess track construction pre-works
analysis, procurement strategies, project documentation, project management
plan drafting, environmental assessment and stakeholder assessment.
Lowood Water Treatment Plant in Brisbane Head Office
John Holland
-
The project Lowood Sewerage Treatment Plant (STP) minor works scope involves
the addition of a new pump skid, pipes and fittings to an existing STP located in
Lowood. There is extra treated water being produced from the existing STP, and the
additional infrastructure is being constructed to deliver this extra treated water
to an existing water pipe, under the Somerset Regional Council, who in-turn is to
deliver the treated water to a sporting facility.
-
The scope of works involves relocation of existing underground earth wires inside
the facility, installation of a concrete slab to install the new pump skid (supplied
by Queensland Urban Utilities) and associated PVC-u pipes and fittings above the ground,
installation of a 300m underground PE pipes to connect the extra treated water to the
existing pipe line under Somerset Regional Council.
Edmonton to Gordonvale (E2G) Bruce Highway Expansion in Cairns
John Holland
-
The project Edmonton to Gordonvale is a Joint Venture with a budget of $500 million between
John Holland, Seymour Whyte and Aecom. The project scope involves the addition of new lanes to an
existing 10km section of Bruce Highway from Edmonton to Gordonvale, including the construction of
multiple pavements, bridges, cycleways and traffic and road lighting works. It also involved the
relocation of multiple railways (under the jurisdiction of both Queensland Rail and MSF Sugar)
and the installation of new cable routes for Telstra and Reef network.
-
The project has multiple engineering teams based on disciple. The main engineering teams are
the Pavements, Earthworks, Drainage, Structures and Public Utilities. While being on the project,
I have worked in the Pavements team (responsible for monitoring and managing the construction of
the road pavements), Quality Control team (responsible for monitoring that the works done by the
engineers are compliant with the MRTS and other Standards), Public Utilities team (responsible
for managing the construction of water ways, road lighting, traffic signals, field cabinets,
power supply systems and optic fibres, etc.) and the Structures team (responsible for the
construction of multiple new bridges and underpasses) during the duration of the project. I have
experience liaising with multiple subcontractors and stakeholders to make sure that the project
is being completed on time.
-
I have been able to identify multiple major gaps in quality of works done by the different departments
while working in the quality department. Some instance of which are:
-
I have been able to identify that the wrong backfill materials were being used as backfill
for multiple pipes (cement, instead of sand) which could potentially cause damage to the pipes
as they do not provide the cushioning effect of sand on impact from vehicle loads. I have raised
this issue with the managers and they have urged the engineers to monitor the quality of works
more stringently as a result since then.
-
Till that time in the project, there were issues with using the wrong class of concrete for
traffic light pole footings and not raising the required Hold Points and Witness Points for the
works that were done. I have raised this with my seniors, and the importance of raising Hold Points
before the works commence has been communicated to all the engineers in a toolbox talk.
-
The project has a concrete register to keep track of all the concrete pours conducted during the
project. The register is in an excel file, and has various tabs to keep track of the order numbers,
pour dates, concrete strength results, etc. Since the original engineer who created the formulae was
no longer working on the project, and no one else knew how these formulae worked, the formulae in many
of the cells in the tabs were corrupted and was giving out incorrect information. This incorrect information
was being used to determine whether to accept or reject the concrete batches used in the project. I have
utilised my excel knowledge to understand how the formulae worked and have fixed these issues. I have also
used excel Visual Basic to automate multiple repetitive tasks in the register (and also in other excel registers).
Maintenance Works on Regional Roads in the Balonne Shire Council
Aramira Civil Engineering
-
While working as a Civil Site Engineer at Aramira Civil Engineering, I was involved
in four major contracts involving road repair and maintenance works in the regional area
of Balonne Shire Council located in Queensland.
-
I was responsible for overseeing procurement of materials and labour on site, managing
and overseeing quality control measures, organizing density tests, ensuring relevant safety
measures are implemented on site, ensuring the relevant Traffic Guidance Schemes are
implemented on site, building a good relationship with the relevant stakeholders, communications
with the suppliers and general project management.
-
I have been able to utilise the knowledge and experience gained from working as an intern at
Macquarie Geotech to assess better the outcomes of some of the negative results obtained from the
density tests conducted on the roads and have able to give feedback on them.
Repair Works on Carnarvon Highway under TMR, Queensland
Aramira Civil Engineering
-
While working as a Civil Site Engineer at Aramira Civil Engineering, I was involved in a project
involving repair works on a 500m section of Carnarvon Highway in Queensland. The project involved stringent
Quality Control requirements at frequent intervals along its length.
-
The project involved stripping of the existing bituminous layer on the whole affected area of the highway
and building a new layer on top to the subgrade. I was involved with the quality control, procurement, quality
testing, traffic control and project management of the project.
-
I have worked with professionals in the field which includes, but are not limited to the Site Supervisor,
Traffic Controllers, Grader and Roller Drivers, Water Cart Drivers, Site Surveyors and the Soil Testers. I have
once met with council representatives to arrange for testing equipment on behalf of the organization.
Effect of Rice Husk Ash and Cement on Soil Stabilisation
Major final year project (Bachelor’s degree)
-
For my major Bachelor’s degree final year project, I have analysed the variance of Optimum Moisture Content
(OMC) of clayey soils with the addition of rice husk ash.
-
It was found that the curve from the moisture-dry density graph shifts towards the right side as a whole, which
indicates that more moisture is required for the in-situ soil to achieve maximum dry density.
-
The practical implication of this result is that the soil is able to accommodate more moisture before maximum dry
density is achieved. This property is extremely useful to strengthen the soil in regions having high in-situ moisture
content, such as regions having high rainfall.
Finite Element Modelling and Analysis of the EIS Research and Testing Facility in Russell Vale
Advanced Computer Applications (Master’s degree)
-
For my Advanced Computer Applications subject, I have been tasked with using Strand7 software to fully model and
analyse a major Research Facility Warehouse Building located in NSW.
-
All the different loads acting on the structure namely dead load, live load and wind load have been identified using
the relevant Australian Standards and have been successfully incorporated into the 3D design model of the building drawn
using Strand7 using available data.
-
The validity of the Finite Element Modelling results have been cross checked with the traditional methods of structural
analysis and they have been found to be consistent with the results generated from the Strand7 software.
CASEY Aquatic & Recreation Centre - Proposed Change Rooms Renewal
Major Project (Swars)
-
While working as a Civil Engineering Intern at Swars in Sydney, I was tasked with the tender documentation, contract
administration, estimation, costing and project management of a construction project located in Victoria.
-
I have liaised with the clients, contractors and other team members to put forward a quote for the project, which is
consistent with the scope of work to bid on the tender put forward by the Casey City Council.
-
Out team has identified the relevant works and materials that are needed for the project to be completed on time and
have successfully been able to win the bid for the project because we have been able to identify excessive wasters on site.